Fremantle Port – Berth 11
Concrete Repairs
LKS Construction

Description
Opened in 1897, Fremantle Port is WA’s biggest general cargo port and Australia’s fourth largest container port. In November 2018, BUSS was engaged by LKS Constructions, maintenance contractor for Fremantle Port Authority, to complete concrete repair works at Berth 11.
Located at the North Quay of the Port, Berth 11 is a heavy-duty berth. With good road access, fitted bunkers, water outlets, electricity and substantial stacking areas this berth is well-suited for the handling of general and break-bulkcargoes, including motor vehicles.
Prior to site mobilisation, BUSS personnel completed the relevant Port inductions and obtained their MISC cards – Australia’s nationwide identification card for the maritime
industry. Berth 11 exhibited extensive areas of spalled and delaminated concrete resulting in the exposure of the steel reinforcement. BUSS’ experienced concrete repair team completed the repair works as specified by Fremantle Ports engineering team; this included the provision of 50mpa concrete with Dramix steel fibres 65/35, bonded to repair surface with Parchen Nitobond EP, thus ensuring a robust and long-lasting repair.
Completed over a four-month period, all works were carried out with strict compliance to the regulations and procedures of the Fremantle Port Authority Act and the Western Australian Marine Act. BUSS’ staging of the repair works around shipping movements ensured there was no disruption to shipping schedule or Port operations.

Figure 1: Concrete breakout (under rebar) underway

Figure 2: 50mpa concrete repair, coated with Concure 99
PROJECT INFO
PROJECT MANAGER:
Graham Murphy
PRODUCT USED:
- Holcim 50mpa concrete (with Dramix steel fibres)
- Parchem Nitobond EP
- Parchem Concure 99
- BASF MasterEmaco 5000AP
POINTS OF INTEREST:
- Buss’ recommrndation of alternate products to address issues of shalloe steel in repair areas was well received by the Port’s engineering team