Exmouth Hospital

Remedial Works

DLR Building

Lyon Street, Exmouth

Exmouth Hospital completed works

Description

Exmouth Hospital, located in Exmouth WA, is approximately 1270 kilometres north of Perth. The town was established in 1967 to support the United States Naval Communication Station Harold E. Holt. In 2009 the hospital became a multi-purpose service, providing additional services besides hospital care and treatment.

DLR Building, acting as head contractor for the Department of Finance, engaged BUSS to complete widespread remedial works to the concrete surfaces and structures of the hospital. The BUSS team mobilised to site in early August 2020 to undertake the repairs, which included concrete repairs, protective coatings and screeding. All works were completed in mid-November 2020.

    Pic 1 extensive concrete cracking to beams

    Fig 1: extensive concrete cracking to beams

    Pic 2 extensive concrete cracking and spalling to underside

    Fig 2: concrete cracking and spalling to underside

    Pic 3 repairs to plant room floor in progress

    Fig 3: repairs to plant room floor in progress

    Pic 4 concrete repairs to external soffit area

    Fig 4: concrete repairs to external soffit area

    PROJECT INFO

    PROJECT MANAGER:

    Graham Murphy

    POINTS OF INTEREST:
    • The hospital, which was at its busiest time of the year, remained fully operational for the duration of the works;
    • Works were completed under a strict programme, to minimise any disruption to the activities within the facility; and
    • The works were successfully completed on schedule, to budget and with zero incidents.