HBF Stadium

Tom Hoad Aquatic Centre Pool Repair and Re-Grouting

VenuesWest

100 Stephenson Avenue, Mount Claremont
HBF Stadium Image 3 Works completed and pool refilled

The THAC indoor pool at HBF stadium is a 50m pool built to cater for high-performance use. The pool regularly welcomes national and international guests for training, competitive and recreational swimming. The elite facilities are used extensively all year round.


In late June 2021, BUSS Group was successfully awarded the tender to complete repairs works and re-grouting of the pool. The remediation works comprised the following scope:
• Protection and support of the movable starting block bulkhead;
• Preparation and cleaning of pool and movable bulkhead surfaces;
• Re-grouting of pool and edge tiles, central return water diffusers and hydrostatic valves;
• Replacement of a nominated quantity of edge and pool tiles;
• Replacement of the construction and movement joints underneath water level; and
• Supply and install the replacement hydrostatic valves and diffuser cover.

HBF Stadium Image 1 Pool emptied prior to work commencement

Fig 1: Pool emptied prior to work commencement

HBF Stadium Image 2 Removal of joint material

Fig 2: Removal of joint material

HBF Stadium Image 3 Works completed and pool refilled

Fig 3: Works completed & pool refilled

PROJECT MANAGER:

Graham Murphy

POINTS OF INTEREST:

  • BUSS completed the original work scope as well as a large amount of unexpected work, resulting from latent conditions, and all work was completed to a high standard and with minimal impact on the original project completion date; and
  • Positive feedback on work quality and project delivery was received from all stakeholders.

LATEST PROJECTS

mend street jetty

Mend Street Jetty

The Mend Street Jetty, located on the southern shore of the Swan River and constructed circa 1975, operates as a Transperth Ferry Terminal. It’s understood

Read More »
HBF Park 1 repairs external brickwork

HBF Park

HBF Park, formerly known as Perth Oval and located close to Perth’s CBD, is a sports stadium which hosts sporting events as well as concerts.

Read More »
Johnson Court 1 demolition

Johnson Court

Johnson Court is a ten-story development comprising 120 retail and residential properties. Cracked bricks on the upper floor balcony nib walls, on the western elevation

Read More »
KRSP Balgo Community Image 3 Joint sealing works in progress

Balgo Community

Balgo is a community located within the Shire of Halls Creek, off Tanami Road, in Western Australia. Established by German missionaries in 1939, Balgo lies

Read More »
HBF Stadium Image 3 Works completed and pool refilled

HBF Stadium

The THAC indoor pool at HBF stadium is a 50m pool built to cater for high-performance use. The pool regularly welcomes national and international guests

Read More »
1 Hardy St Image 1 Western facade of Riverview Apartments

Riverview Apartments

Riverview Apartments, located in the heart of South Perth, is a brick and concrete structure comprising of 63 apartments over 9 levels. An inspection of

Read More »
Fremantle Jetty Pic 4 pile wrapping works in progress

Fremantle Jetty

The jetty facilities in Fremantle include the existing jetty, one main wharf, a finger jetty and a wall of wave attenuators; there is also mechanical

Read More »